Project Status Presentation Template

An 8-slide project status template: RAG status, milestones baseline vs forecast, progress, risks and issues, decisions needed and the next two weeks.

8 slides4 min read

Opens in the editor with a free 7-day trial (no credit card, up to 5 presentations). Trial exports are a watermarked PDF; clean PDF and editable PowerPoint export start on paid plans from $8/month.

Preview the deck

These are the first, middle and final slides of the editable deck that opens when you use this template, rendered with the SlidesMate editor. The sample organization and figures are fictional; replace them with your own.

Slide 1 of 8 · Project Atlas: Status Report #9
Slide 5 of 8 · Risks and issues
Slide 8 of 8 · Next report: November 27

Project Status Presentation Template

This project status presentation template is a recurring report for sponsors and stakeholders. It covers the overall status, milestones against baseline, progress since the last report, risks and issues with owners, decisions needed, and the next two weeks of work. The sample deck is a fictional CRM migration, Project Atlas, at its ninth fortnightly report with an Amber overall status.

The project, people and dates are fictional. Replace the bracketed owners with real names.

The deck reports on work under way. For a team's regular meeting agenda, use the team meeting template. For future product priorities, use the product roadmap template. To request approval for a new project, use the project proposal template.

What's in the deck

#SlideLayoutWhat it needs from you
1Project Atlas: Status Report #9CoverProject, report number, period, overall status, PM and sponsor
2Overall statusMetricsSchedule, budget, scope status and percent complete
3MilestonesTableMilestone, owner, baseline date, forecast date, status
4Done since the last reportBulletsThree to five outcomes
5Risks and issuesTableItem, type, impact, action, owner
6Decisions neededNumbered listEach decision with who must make it
7Next two weeksTableTask, owner, due date
8Next report: November 27ClosingNext report date, expected status, contact

How to adapt it

Put the status on the cover (slide 1). Some stakeholders will only see the first slide. The overall status, report number and period should be readable without opening the rest.

Define your status colors once (slide 2). Red, Amber and Green are only useful if everyone reads them the same way. A common convention, which you should adjust and write down for your project:

  • Green: on track. No help needed.
  • Amber: at risk, with a recovery plan the team owns.
  • Red: won't meet the baseline without a decision or help from above.

Report schedule, budget and scope separately so a Green budget doesn't hide an Amber schedule.

Show baseline and forecast side by side (slide 3). This makes slippage visible without commentary. If the baseline changes, record that it was formally re-baselined and when. Don't overwrite it.

Report outcomes (slide 4). "Sandbox configured and access granted to 40 test users" is an outcome. "Worked on sandbox" is not.

Separate risks from issues (slide 5). Issues are happening now. Risks might happen. Every row needs an action and an owner. Without them, the table is just a list of worries.

Make escalations explicit (slide 6). Write each decision as a question, with who needs to decide and by when. If there's nothing to decide this period, say so. That is useful information too.

Commit to the next two weeks (slide 7). These tasks are what you'll report against next time, which keeps reports consistent from one to the next.

Weekly, fortnightly or monthly?

CadenceFitsAdjust
WeeklyFast-moving projects, or near go-liveShrink slide 4 to the top three items. Slide 7 becomes "next week"
FortnightlyMost delivery projectsUse as is
MonthlySteering groups, long programsAdd a budget table and a milestone chart across the whole program

Common mistakes

  • Reporting Green until the week before a deadline is missed.
  • Quietly moving baseline dates.
  • Risks with no owner or action.
  • Burying a decision request in the risks table instead of asking for it.
  • A different format every report, which makes trends hard to follow.

AI slides for team meetings covers standups and recurring updates. How to present data effectively helps with milestone and budget charts for monthly reports.

To draft a report from your project notes or tracker export, paste them into Create.

Frequently asked questions

What should a project status report include?

The overall status, with separate schedule, budget and scope indicators, milestones against baseline, what was completed, risks and issues with owners and actions, decisions needed, and the next period's commitments.

How long should a status presentation be?

Short enough to cover in 10 to 15 minutes. Eight slides with consistent content each time lets regular readers find what changed quickly.